Sprint E-Solutions, Santa Clara, CA 160,000 SF co-location facility. FMB's scope included full N+1 redundancy, 6,000-ton central plant, fuel oil systems, piping and ductwork. Project was executed in six months. CD: '02
Raging Wire, Sacramento, CA 190,000 SF data center. Fast-track project with 30 day design and engineering process and four month construction schedule. Designed and built by FMBDBC CD: '01
Teale Data Center, Sacramento, CA Premier data site for the State of California. 2550 tons total with N+1 redundancy. Emergency power with 48-hour fuel capacity. Designed and built by FMB Design/Build. CD: '00
Frontier Global Center, Sunnyvale, CA Large co-location center. FMBDBC performed demolition and retrofit on this 100,000 SF facility. Scope included design build of plumbing, closed loop water-cooled HVAC system and condenser water piping designed to remain operational after an 8.0 earthquake. CD: '99
ISO Data Center, Folsom, CA State computer center. FMB rebuilt two 360-ton chillers, added cooling towers, boilers, circulation pumps, pneumatic control work and modified ductwork. CD: '97
|
|
| |

Other Projects:
Caspian Global Center, Sunnyvale, CA — Large co-location
facility. FMBDBC performed demolition and retrofit on this
100,000 SF facility. Scope consisted of plumbing, closed loop
water-cooled HVAC system and condenser water piping. CD: '01
Sprint/MCI. Sacramento, Dublin and Pleasanton, CA — Mission
critical data centers. FMB installed complete mechanical
systems. CD: '01
AT&T. Manchester, CA — Telecommunications
facility. FMB retrofitted the mechanical systems for this
remote facility without disrupting its critical operations.
CD: '00
Telephone Building D, Roseville, CA — 80k SF,
two-story office building. FMB installed a raised floor air
distribution system and a custom cooling system. CD: '00
Telephone
Warehouse, Roseville, CA — 110k SF, office
warehouse and energy center. FMB performed HVAC, plumbing,
piping and ASM. CD: '99
|
|
|